GP Bulk Oil Storage Terminal is located opposite to GP’s new plant (Plot # 2J01& 2J02)
At Hamriyah Free Zone, Sharjah, United Arab Emirates.
The Storage Terminal is connected through underground pipeline (12-inch x 2) with
Bunkering pit from main jetty of Hamriyah Free Zone Sea Port.
This new state-of-the-art Oil Storage Terminal Have following facility.
- Phase One Base Oil Storage Terminal:
Capacity is 1731 CBM X 8 Tanks = 13848 CBM
Phase 1 construction was completed in 2019, and the operation
started in March 2020.
- Phase Two Base Oil Storage Terminal:
Capacity is 2260 CBM X 12 Tanks = 27120 CBM
Construction was started 01st December 2024, and it is completed on 17th April 2025.
Operation will start in June 2025.
- Phase Three Base Oil Storage Terminal:
Capacity is 6000 CBM X 4 Tanks = 24000 CBM
Phase 3 construction will start in JUNE 2025.